by tyingq · 10y ago · 0 comments
Anything a business is going to invest in needs some kind of justification, and a metric to prioritize against other things the funds could be spent on.
I think it's fair to push back with suggestions that might make a realistic estimate possible (reduce scope, proof of concept, etc). However, just suggesting you can't provide any kind of reasonable time and cost estimate doesn't help anyone.
The tack of the article was "Estimates can't be done". Which is silly. It presents this analogy: "would it really have made sense to ask Einstein how long he would take to find a unified theory of physics?"
I'm sure there's some small amount of software work that might fit in that space. I would also guess that the vast majority of it doesn't.
You can plug these into monte carlo simulations with any kind of math happening between your uncertain terms, get output distributions, pick bounds to minimise risk (95% chance the release is completed on or before <DATE>).
The essence of my point was that flat out not estimating isn't an option.
Sometimes it is better to start developing and then tell stakeholders that it will take a really long time when you run into problems. A lot of stakeholders have problems with estimates of the form "it could take 2 days or 3 weeks". It would be nice if the industri starts giving probability about estimates especially when you know that there are two clear possibillties where one is much, much larger. They might want to invest 2 days into trying to solve the problem with the understanding that it might take much more time and if that happens they can change their mind and skip the feature instead, "only" wasting two days of investigation.
People need to understand that there is no zero-cost instrumentation and getting measurement wrong is extremely expensive.
I have to work backwards from deployment to development or there are problems. Sometimes there are external lags of months between them. People find my line of questioning in this regard very annoying but I do this and others on the team/teams do not, and I have a much better accuracy rate. So they've learned to do this with me.
When you're deploying, you're designing a protocol and that's always a challenge. But if you don't do it, the error rate creeps up.
I publish a statement of work for each release point and encourage redlines to that. So far it's not drawn any fire. But inadvertently getting a feature in before it's handed off properly causes lots of problems.
The critical resource is always human attention.
Of course, if you can't be more precise than that, chances are that there's some other piece of work that's more easily estimated, and has a more concrete ROI. That work would logically come first.
But there are times when you don't know. So you handle that by saying something like "I don't know enough now to give you any kind of an estimate. In a month, I'll be able to do enough research that I can give you a realistic estimate." If management will accept that, congratulations! You have management that is willing to live in the real world.
But you can't even always do that. I was asked to estimate how long it would take to port something I'd never had to touch before. Well, I don't know. Worse, I don't know how long it will take me to find out, because I don't know how many obstacles I'm going to hit, or how long it takes to get past each obstacle. I'll know when I'm done; I don't know any more precisely than that. I mean, I can say something like "probably less than a year", but I have no idea how to do better in that situation.
If I've done it before, or something enough like it that I actually could tell you how long it would take, then you are wasting your money and my time by asking me to repeat the work.
If you hired me because you wanted me to do the same thing for you that I once did for someone else, and you therefore expect me to be able to tell you how long it is going to take, then I will start polishing up my resume, because I made a mistake when I accepted your offer.
What I'm saying is that it doesn't matter if it's a software project, construction project, etc. If the potential amount is non-trivial, it's bad business to commit to a completely unknown amount of spend.
If you can't say that the spend < benefit, you really shouldn't do the work. It's basically speculative investment at that point.
That may be something you personally aren't on the hook for. But, in most cases, there's some option to get an idea. Bids from outside software development shops, calls to companies you partner with, small scale prototype, agreement to spend a fixed amount and re-evaluate, etc.
Software is nothing like construction. We don't build bridges, we draw blueprints for bridges, which our construction robots then build overnight; if it's a good bridge, millions of other construction robots go build millions more bridges just like it. If the bridge doesn't work, we have the construction robots tear it apart, and we try again with another one the next day.
When we get good enough at designing bridges that we start to see the patterns involved, we build a robot that draws bridge blueprints, and we have the blueprint robot tell the construction robots what to do while we sit around and think about urban design theory. When we get good enough at thinking about where bridges ought to be placed and what attributes they ought to have, we build ourselves a highway-design robot that orders around the bridge-blueprint robot that orders around the construction robots, and then we move on and start thinking about something more interesting.
Software is basically speculative investment. That is why we make the big bucks when our projects succeed.
edit: fwiw, construction projects often touch on "exploration into the unknown".
Also, you are arguing against "accurate estimation". I'm arguing against the premise of the article. "No kind of estimation is possible"
Edit. Nobody is asking for made up numbers. They are typically asking that engineers participate in a reasonable discussion to try and get some criteria to make a decision. "I couldn't even say 1 week vs 10 years" is just as silly as "I want an exact number".