by ljw1001 · 8y ago · 0 comments
Many organizations have common characteristics in this regard. First, they don't expect you to be on time. Sales may think you're going to launch on time, but it's in their financial interest to think so. The rest of the org probably made a schedule they know you can't meet because they think it motivates you to work harder.
Second, unless you're in a startup where everyone's inexperienced, most people probably already know you'll be late, but aren't saying it out loud. They likely have discussed it (up the chain) in meetings you're not in.
Third, people do shoot the bearer of bad news. You can earn a rep as a negative person if you make _true_ predictions out-loud that don't fit the common desire. This is especially true if some of the senior people who know (like your boss) haven't been forthcoming with their bosses.
Have a quiet conversation with your boss over lunch or beers - not a meeting - and tell him/her what you think. Be prepared with details, but if he/she doesn't ask for them, don't provide any. There's a good chance he/she already knows as you suspect.
Even more casually (lunch/beers), express your concerns to the project owner. It's probably not new news to him/her either. Being "positive" is a huge part of the corporate game.: Again, if no details are asked for, don't provide any. Shift the conversation to the weather or the world cup.
You're now down. Go back to work.
Next step, is to spell this out to your project team leadership completely unvarnished. Tell them your conclusion and how you got there. Don't let them bargain over your reasoning unless they actually have better evidence. The key is to never say "this is too hard" or "we don't have enough people" or make any other excuses. Not should you be overly emotional. Just give the facts. It's a fait accompli.
Then just ask how they want to deal with it. There is absolutely nothing to be gained from beating around the bush. I've done this more than once and was always taken seriously. One time we had even already signed a fixed-bid contract before I was able to give them an estimate. What you've committed too doesn't change the course of what's actually going to happen.
You had leaders who were willing to listen to facts rather than prioritize consensus (which brings with it the belief that because you were the dissenting voice in the room demonstrates you're divisive and a problem).
You landed in a really good culture, just one that hadn't faced reality yet. You've yet to plumb the depths of corporate America. :P
Here's the crux of the matter. Your approach needs to be tailored to the culture you're in. The higher up in the leadership chain you go, the more important your understanding of the political machinations of your company is.
All corporations have politics, even the smallest startups. Some are just more cutthroat/feudal/kafkaesque than others.
Lets say you were in charge of the project, are intimately familiar with the technology, and had a clear plan that would lead to success but upper management wasn't happy with the timeline. Their goal seems to be to quickly complete this project to display it as a "win".
Now the new manager was brought in, does not understand or care to understand the complexity of the project, and just keeps asking "when will it be done". Then got tired of that and changed to have it done in 2 weeks which is unreasonable, and then gave you an entirely false, negative performance review based on information they apparently forgot to actually verify or they would have known it was already complete and the people who were on the receiving end of the product are incredibly happy.
HR is asking for a meeting to discuss, what do you do? Tell HR about the depth of the incompetence Tell HR you weren't getting support from upper management Tell HR to look into what on earth was the reason this specific manager was selected.
or
GTFO?
This is a real life circumstance I am dealing with. I believe in the technology but unless changes are made it will be a guaranteed failure. Upper management likes the technology and really wants success here, but I know it wont happen unless then changes are made, and the people between the senior executives and me are making it impossible to be a success.
I should say that I've learned this over many years, but have applied it at the highest levels of corporate America and it does work. If you present an estimate _with evidence_ it makes it so much harder for even the most grizzled IT exec to argue against you. Most are still used to thumbs in the air so if you give them something tangible, they will actually love it.
As a borderline autistic person I have a very direct communication style and lost account of how many times I burned myself for failing to "beat around the bush".
You can't say "the project is doomed" even if it is true. You can't say it will be so over budget and take so long that it would be better to cut the losses now. Don't expect to go unpunished for saying "the king is nude".
According to my experience both parents are absolutely right, but the first is how most organizations work and the second is an ideal seldom found in the real world.
In some, you actually have to "earn your place" in the company, and most recommendations I've seen are "keep quiet and listen".
This works pretty well in smaller companies or startups, but corporate culture is usually political enough that it would be a disaster for your career.
> Then just ask how they want to deal with it.
Disagree. Anytime you find a problem you should come up with at least two solutions before you bring it to leadership. Managers hate people that only come to them with problems. You're closest to the project and you should be the one to know the situation and possible solutions.
Yes. I think many people who believe they were punished for delivering bad news were actually punished for not offering ways to solve the problem. It's easy to simply say, "the project is doomed" and leave the problem in management's lap; much harder to come up with creative ways to rescue a bad situation.
Only one time?? Are you hiring? :)
You will never be thanked for telling them uncomfortable truths, even if they -don't- know. Even the private conversation is dangerous; as you say, keep it as low key and minimal as possible ("i have some concerns about the timeline" is literally all you should say unless they ask, and your answers to any followup question should be equally circumspect).
Instead, as others have mentioned, just make sure you document what does get done. Ideally have a decent backlog of things that need to get done, but that presumes a PO who does their job (and it sounds like he/she probably isn't). That's your CYA, and your innocent response if they ask why you didn't raise the alarm.
Deadlines often slip. It happens ALL THE TIME, regardless of elaborate and sophisticated project management techniques and skilled contributors. Deadline slippage is also RARELY FATAL, but yeah, leads/PM's can absolutely get themselves metaphorically shot by bearing bad news to the wrong people at the wrong time.
Some orgs hire a ridiculous number of PMP's who pretend like they're making a difference but are really just practicing an elaborate dance of goal-post-moving to appease the deadline-gods. People in such orgs often bullshit about a "track record" of being "always on time and under budget".
Best thing OP can do is learn from the mistakes and speak up next time during planning phases, well before deadlines slip.
Always wise to know what the corporate culture is around these kinds of things.
Corporate culture includes everyone involved in a project. You can't be calm if you have someone outside of your office going mental over something being a day or a week late.
I've seen this so many times, it's like why even bother attempting to describe what we'll deliver. Just put the date down.
How do you know deadlines are going to slip when planning the project? Makes no sense.
Surprisingly, it works relatively well to estimate how long the project will actually take.
It falls apart if you're talking about 10's to 100's of people working for weeks/months/years, or wherever you need to compete with other vendors for the contract.
3 hrs => 6 days
2 days => 4 weeks
If you actually want to have some integrity when you talk about deadlines before it eats up your insides and you lose sleep you will need to have these beer / lunch conversations to gauge the level of appetite for change and then start talking about how to get something shipped on time as well as the consequences for not shipping on time.
Sounds like you already have this dialog with your manager. Keep talking about how best to manage expectations up the chain.
You’ll want to get buy-in to reduce scope or make whatever other changes you need, otherwise you’ll have to lie to keep up the facade that things will ship on time. It will burn you out.
If the read in the parent comment is bad for your org and it’s NOT normal to BS deadlines and ship late then no paper trail or written warnings, risks, and issues brings with it some badness as well - judge for your organization. I’m guessing you may already know the answer.
This is probably not the best career ladder advice at some firms, but at all costs make sure you never lie for anybody. Keep your integrity. Be honest. Sleep at night.
Of course sometimes “honest” is an excuse to be pessimistic. Look hard to make sure your dire warnings are not “chicken little” pessimism, then talk it out with your management, but don’t lie for them and be honest about your engineering and your team.
> a rep as a negative person if you make _true_ predictions
> out-loud that don't fit the common desire.
I've heard this very often, both as advise, complaint and even in an intimidating manner. And yes, I've seen this, people who stay kind of positive stay in their position even if they screw up a project completely so it has to be "rebooted". In fact I've also observed a super negative person, being a colleague of mine for 2.5 years and staying good with everybody despite one screwed up project.
On the other hand people have put me in various settings under high pressure to keep my mouth shut both internally and externally. (That was only in the startup/co-founding setting though.)
My conclusion: I'd take this advice with a biiiiiiig grain of salt. In my experience people get away with everything as long as they stay confident and keep their shit together.
Disclaimer: I'm not a team lead
You can be a negative/realist as long as your perceived value outweighs your "bad" attitude. The problem with this is that people are really bad at placing value on soft skills and all it takes is one clueless manager to sandbag you.
Everything op said above is spot on
But I mean for anyone with team responsibility: staying silent is bad for you, which is okay if you're in for the career. I totally respect that, people should be ambitious if they want to. But this is the recipe to make workplaces toxic and bad for the whole team.
You do need to figure out for yourself a realistic, pretty safe time when you will be ready: an extra month? three months? never? You say the work is outside your team's comfort zone. This is potentially a much bigger red flag than being late. Will the team learn and deliver, or it just cannot execute at the speed requirements are changing or will soon be? Be brutally honest with yourself.
If you think you can safely deliver the product in, say, three extra months, then keep working but be ready with good estimates when the time comes to redo the schedule. When that discussion comes (usually suddenly), having a clear plan and realistic estimates that you can confidently present will likely give you (most of) what you ask for. IME really bad options are either agreeing to fix everything in a week (if you know it will take three months) or not having an estimate at all "we are burning midnight oil and I cannot tell you when we will be done". Either could lead to quick problems.
IME when "what do we do with this crap" time comes, senior management does not care why you are late (everyone is at least some of the time). They want to know if you have a plan and look ready to execute it. Just my 2c. Good luck!
Like some of the other posts said - be real. If people don't respond well to this then the company has a bigger problem than a slipped schedule.
One sign this isn't healthy environment, frankly, is that no one has (apparently) asked the lead how he/she thinks the project is going. This also suggests that they already know and/or don't want to know.
OP's description is generally how every project at every company has ever worked, forever.
True. But under such circumstances chances are pretty good someone(s) is going to be shot anyway.
I think the answer is solid. But if going this route I would update my resume and reach out to my network.
If this ends badly you want to be prepared.
As someone who has been a bearer of bad news, this is a sound advice. Most of the time you are told - "At least give it a try". And even if you tell them - "I did try but still likely we will miss the deadline". They will ask you to check again.
It is mind-numbing when it happens the first time. And most of the time you get disillusioned and think - "I need to look for another job". Guess what? Every corporate works like this. All about positivity and "You can do this" messages. And most importantly people setting up super-aggressive timelines knowing well that you are going to fail.
> Second, unless you're in a startup where everyone's inexperienced,
Curious about this though. So, as per you startups are run by people who don't know how to run projects?
If however the project is due to slip 200%, or 400%- I guess I don't have specific advice, but that kind of project is the sort of project that can sink a company. Of course, you only really get to that point if vice-bigwigs are lying severely to the bigwigs, in which case there may be nothing a team lead can do about it.
Also be prepared with solutions. Any decent manager or product owner is going to ask things like: "What's a realistic timeline?" or "What could be cut to get closer to the timeline?"
It would worry me more if they didn't ask details. In my experience that means they sent you on a fools errand expecting you to fail and take the heat for it.
First they hear what they want to hear, i.e., what is not threatening to them. 'Project delivery will certainly be late' is heard as 'the next milestone will be late' or 'we're a little behind schedule and will catch up' or 'it's making another project late', etc. It's truly incredible what people will construct in their minds. What's the saying? 'Don't expect people to understand what their salary depends on them not understanding'?
Second, like everyone, they ignore or put off dealing with bad news. (Probably, that's a temptation of the OP.) Then they say, 'I didn't know.'
It depends on the people and the organization, of course, but you do you protect yourself from being thrown under the bus?
It can compel some attention and provide an opportunity for extra thought. An unwanted verbal message over lunch is easily forgotten or misremembered, intentionally or not, weeks or months later. A written one is harder to ignore and provides something the recipient can re-read and ponder later.
Also, there are circumstances where documentation is good to have. For example, it may help in a company with more layers; your email to the guy 2 layers up may help when the guy 4 layers up gets involved.
It's her responsibility to help the rest of your business do the best they can with reality. If sales of your existing product have dried up because prospects are waiting for the modernized one, that's a big problem (been there). But it's a problem belonging to product and sales management, not you. Unless you are a founder.
Renovating software is hard, much harder than greenfield software. All the best to you.
If you're in a smaller company, and you have clout due to being closer to the top of the food chain, and you have a vested interest in the success of the operation, to the point that it's worthwhile cutting your losses and moving elsewhere if the outcome isn't positive, then the higher risk strategy of pushing for change makes more sense.
However, these things happen time to time and when you have a stubborn PO like that from the beginning, you should have started looking elsewhere way before as a lead role. I’ve never heard of situations where a manager takes the blame. It always falls to the engineers.
If you do too much boat-rocking, though, you may find yourself looked on as "external" to the other responsible people, which is not a good place to be.
1. Focus on something going well. 2. By the way, could you fix this little thing? 3. Return to positive stuff.
This formula can be applied to delivering honesty amid positivity. Ideally whoever you're communicating is mature enough to just take honest feedback straight, but if they aren't then this can be a safe(r) way to deliver it.
Bearers of bad news are frowned upon when the bad news is their fault and not presented when its determined to exist. I think this is a distinction that should be made with your phrase.
1. A small course correction can work wonders early on, but if you wait until the ship is seconds from the iceberg there’s nothing anyone can do. Or use the cancer analogy: early detection can be the difference between life and death.
2. Yes, sometimes deadlines are padded and you’re silently expected to miss a little. Sometimes they are not and you’re not. How do you know which one applies to you and your project?
3. Having private conversations is fine but private conversations can be denied and privately made decisions do not become the broadly understood plan of record, leading to confusion and ambiguity, which are risk multipliers.
4. A positive attitude is good and hiding real problems, evading responsibility, and playing corporate games might work in the short term. However if that becomes what you are known for, it will limit your career long term.
That constructive feedback is actionable and adds value. If your manager (or the business) chooses to ignore it, don't be frustrated, but when it's constructive, finite and actionable, you'll be surprised how often they'll make the changes.
If you've been there for 3 years and never had a drink socially with the PO (who presumably OP doesn't report to other than in this status report context) then you suggest it just so you can talk about how you're not hitting the schedule, it's possible they don't take it well.
“What happens if the deadline slips?”
If the project is late, does the company go out of business? Do people get fired? Is the overall deliverable unusable within the org? Is the deal lost?
If the answer to these is a big “no” then totally agreed with OP to not sound an alarm.
However configuring a skilled team and leading it to do excellent work and constantly improve should be something most people strive for.
NB Based on one fairly large project I was involved in for a large company where there was a huge drive to get the system delivered on time then.... nothing. Nobody used it for months.
Eventually we found out about the real reason.
As long as you are sure you will eventually succeed, ignore the problem and keep going. Being late is no big deal; it's actually a confirmation of how amazing and innovative your product is.
If someone senior brings up the issue, don't flinch, and be ready with an alternative timeline.
> The rest of the org probably made a schedule they know you can't meet
> Most people probably already know you'll be late, but aren't saying it out loud
> There's a good chance <your boss> already knows as you suspect.
> It's probably not new news to <the project owner> either.
Doesn't take much for one, if not all of those to be untrue. And by the time it unravels, it's too late.
If you do this, follow it up with an email outlining everything you said so you have a paper trail that you brought it up with your boss.
That’s just bull.
If your organization isn’t willing to get real and is blaming people instead of processes, it’s the wrong org to be.
Just say things as they are. I’d just raise this in my 1:1 with boss and boss’s boss. “It’s highly likely that we’ll miss X deadline, because of Y reasons. Here are some options we have. Either cut scope to meet deadline, pull in more resources for Z work, that can be parallelized, or push back the deadline.”.