by Balgair · 7y ago · 0 comments
Take whatever time I think it should take. Then double that number and go up one time unit.
Exp: I think it should take me 3 hours this afternoon to do this -> 6 days.
I think it should take me 2 days to to this -> 4 weeks.
I think it should take me 1 week to do this -> 2 months.
I think this should take us one month to accomplish -> 2 years.
Would you rather deliver a product with finished surfaces or cut corners? Proper design and good overall test coverage, or zero budget for maintenance?
It also helps to understand that management will ultimately decide that we need to do the project in half the time, and with these extra features you didn't ever plan on building.
My budgeting strategy is to always assume that for whatever scope you have planned, 50% of the complexity that you will need to deliver in order to reach the finish line, remains unknown at any given stage of planning. Compensate upward if there still remain known unknowns.