by hfkajshfaks · 7y ago · 0 comments
A line goes out.
while (there some lines are still live):
The current redistributes itself among neighboring lines.
Neighboring lines trip
end
BlackStart()
BlackStart() is fun. Having your plants and grid down is like having a dead battery (plants use ~30% of the electricity they gen on themselves) and no one to give you a jump.Usually the hydroelectric plants are started first. Arg. is lucky, they have a lot of those. Otherwise you need to fire up diesel generators (which hopefully have been maintained).
You give power to the grid first so you can start another plant.
Then you feed hospitals and continue firing the thermal plants.
Throughout all of this you have to keep phase stability (no grid, no phase reference). I'd assume this would limit renewable's use-fullness for re-start (a thousand 5Mw turbines out of phase are best left idling)
As a last step you turn on your nuclear plants (Arg. has a few). These are last because of nuclear poisons that accumulate from decaying wastes that weren't burned while the reactor was off.
It's a bloody hard problem.
I forget the exact calculations involved (it's been years and I'm no longer involved with that area of operations), but you want to make sure your frequency matches the grid you're connecting with to within a certain amount. I think the stations which connect neighboring areas usually have extra monitoring equipment for a variety of energy accounting reasons, but also to measure the frequency on each side to see if it's a go or no go. I believe they use synchroscopes (https://en.wikipedia.org/wiki/Synchroscope) to do this.
Edit: it looks like y'all started talking about this below and I missed it, but the information is good, so I'm leaving it up.
> Neighboring lines trip
> As a last step you turn on your nuclear plants
...don't get it: why would you turn off your nuclear power plants, even if the grid failed?!Won't it make more sense to keep it running as usual maybe just using the power to generate steam that you throw into the atmosphere? ...mainly because stopping and restarting a nuclear power plant is expensive af.?
(It still boggles my mind why are electric grids so focused on efficiency at the cost of resiliency... with abundant nuclear + hydro you could easily over-produce a bit, I'm 99% sure that making electricity dirt cheap for consumers by gov controlled over-production would help fight climate change even if it appears wasteful: there will be huge incentive to replace petrol burning trucks, buses, cars etc. when electricity it dirt cheap... and then prices can be gradually ramped up after everyone made the conversion.)
The key factors seem to be:
1) the plant must be capable of running as an island. It seems not all of them are; I suspect the problem is the plant consuming a variable amount of self-power e.g. 1MW being connected to a 100MW generator results in a very unstable system.
2) whatever safety event causes the problem must not trip at the generators themselves but disconnect the plant cleanly from the grid. Since these events are by definition exceptional, this may be very hard to avoid.
> with abundant nuclear + hydro you could easily over-produce a bit
Both of these are exorbitantly expensive to build, and hydro requires specific geology.
How many people have a manual transmission car just so they can pop the clutch if the batter is dead.
A better question is, should we have nuclear power at all? I took classes in nuclear engineering, by friends are nuclear engineers, ect. but it's not obvious to me that cheap electricity is worth it.
Why would you say that? I mean sure, if you can't manage to get cost-effectiveness right then it's not worth it. But otherwise dirt-cheap and readily available electricity is absolutely needed to solve the world's problems! Think about what will happen when large swaths of land loose access to drinking water after climate + pollution wreck things up and the only alternative is ocean water filtration and desalination plants that will need huuuge amounts of power! Also think about massive irrigation and civil engineering projects that will be needed to fight desertifications etc. And to keep heavily populated costal cities above (the new, higher) sea level. That's terrawats upon terrawats of energy that will be needed to constantly shuffle earth and water around, and maybe even to power huge city-scale air filters etc.
We have and still are wrecking up the planet to such a high extent that sooner or later the bill will arrive and we'll need to put heavy effort into re-terraforming Earth to keep it inhabitable... And there really is no other answer than nuclear here, while cities filled with LED-lights and low powered devices and highly thermally efficient buildings can run on renewables, heavy civil engineering projects and land decontamination and producing drinking water etc. will need waaay more power than our blanket of communication equipment and drones.
We could decide not to, but then we'll end up fighting for resources and instead of nuclear power with it's inherent risks we'll get... nuclear wars!
> reactors require triple redundancy for their power supply, including the grid.
Thanks for posting. I learned something interesting today.
I can imagine the consequences of a total loss of power in nuclear reactors...
I'm curious about the statement about renewables though because it seems that with wind or solar the production is very irregular even in normal operation. Doesn't that mean there has to be some technology to balance individual generator differences which would make re-starting those installations easier?
Re: Nuclear, how much energy is required to start up a nuke plant? If decaying toxins are a risk shouldn't those be prioritized? I might misunderstand what you mean by toxins, does that reduce production for some time?
This proves problematic during reactor startup. Since it's absorbing neutrons, the controllers would need to retract the control rods further out than during steady state in order to achieve a replication rate of 1.0. However, xenon-135 stops being a nuclear poison after absorbing its neutrons... which means the replication rate will increase, and the reactor might run away.
This is part of what happened in Chernobyl, though they'd also disabled most of their safeties. (And dismantled the others.)
Regardless, nuclear poisons are something to keep a very careful eye on.
Xenon poisoning was discovered at the Hanford, Washington, B reactor during the WWII Manhatten Project.
https://www.osti.gov/opennet/manhattan-project-history/Event...
In future I would expect renewable and storage elements to provide black-start frequency reference.
There are also organizations like the RTO/ISO that also act like air traffic controllers for the grid by keeping it reliable. They also are usually responsible for committing and dispatching generation for dozens of utilities collectively to save money (by banding together, you need to carry less reserves or backup power and can leverage economies of scale). In North America these organizations are (CAISO, SPP, ERCOT, MISO, PJM, NYISO, and ISO-NE). All of these organizations practice black-start drills (I used to help run them) and have NERC certified operators.
Close. My dad's a power engineer, specifically grid protection.
The transmission level engineers and operators will call the shots as far as how the high level stuff goes down. In other words they'll issue a directive to get unit x online and then close in breaker b and clear a path to unit y while picking up load at z. The actual process from the end of the people doing that work is likely to be significantly more detailed.
Each utility generally has its own black-start procedures. One utility might start two diesel generators (only really used for black-start) and then slowly start energizing the path to various loads and other generators. That utility and it's parent RTO/ISO train on that scenario several times a year and have the procedure printed in a binder within reach.
Something I've found interesting is that many of these plans are ~35 years old and we're created before computers were super common place for these kinds of things. The point being people weren't doing graph and optimization algorithms to determine the optimal paths. There has been a little university research and national lab research into this recently and I've heard they've helped certain utilities that they worked with determine some improvements, which is always exciting.
My dad's a power (line protection) engineer, everything I know is from talking to him.
I love how the people coming from different fields invented their own word for "the process of starting a system through external intervention because it cannot support itself at this point".
Kickstart. Jumpstart. Bootstrap. And now I learned a new one: blackstart.
[1] Synchronizing AC generators -- Part 1 (introduction and sync lamps)
[2] Synchronizing AC generators -- Part 2 (strobe light view)
[3] Synchronizing AC generators -- Part 3 (sync and unsync)
[4] Synchronizing AC generators -- Part 4 (phase deviation)
The first video explains all the concepts and shows a sync, but the later videos bring additional conditions and detail.
[1] https://www.youtube.com/watch?v=RGPCIypib5Q [2] https://www.youtube.com/watch?v=sFohkp2aaU4 [3] https://www.youtube.com/watch?v=GRk_qJxaxh8 [4] https://www.youtube.com/watch?v=RT1ySBc-Bls
Phase is monitored on both sides of the connection, and high voltage contactors complete the circuit when tolerances are met.
I've been to about 30 stations under 50 MW and the biggest station load might have been 300 kW if they had all the heaters, fans, pumps, crane, welders, air compressors, and gates operating at the same time.