by alexhutcheson · 7y ago · 0 comments
If you use this method, it's absolutely critical that the team always focus on relative effort, and not on time. If you want it to continue to work, you also have to be very careful how you communicate with team members regarding their progress and estimated completion dates - don't tell them that their component is "late" - this will make them think in terms of time next time you're estimating something, and will ruin your estimates.
This doesn't work. The problem is that you get periods where the work is relatively easy overall so 5 points ends up being tasks that take 2 days. Then you pick up new difficult features and estimate everything relative to all of the new hard tasks and you end up with 5 points meaning 5 days.
Sure you can gauge relative difficulty of tasks between each other, but in a regular developer's day-to-day life the range should really be 1-100 or so rather than making stuff fit into 12 points or less.
2. Don't use a short time interval or moving average to determine your points->time mapping. You're looking for the long-run average mapping, not a specific estimate for this developer today.
I think we should always have reference tasks in front of us -
Step 1: Figure out how to do this
Step 2: Do it
Estimation is incremental - sometimes you need to spend some non-trivial effort gathering the information you need before you can estimate the relative effort in building a system.
this is the crux of the issue.
on average you can estimate six month of work if you spend two weeks chopping it into tiny bits. rarely management allow that to happen and developers are rushed in with aggressive randomness.
these "developers are bad at estimating" pieces are mostly people that try to estimate effort from complexity which is the wrong approach a priory because complexity hides the project unknowns, and this methodology, along all other comparative methods, is just a Gaussian curve built out off gut feelings: sometimes converges to a realistic estimate for large enough values, but more often than not the center just shows the developer team bias.
Throughout my career, tasks which can be estimated relative to similar or identical tasks from recent history are the exception, and the rest is indeed gut feelings on complexity.
Step 4: Go to step 1
I'd be interested in reading the research you're referencing, if you have something specific in mind.
Specifically, the PSP (Personal Software Process) suggests using LOC as a proxy for size. e.g., a Small task might be 50 LOC, 200 LOC is medium, 700 is large. Then you can take those T-Shirt sizes and compare them to tasks you have done in the past and use that historical data to predict completion times.
I'm simplifying it somewhat (e.g., there are also Complexity inputs), but the process does work if the organization is disciplined enough to follow it.
FWIW, I "feel" the big issue is with loosely defined requirements which shift as development progresses.
And yes, while unmanaged, changing requirements is a major problem, even with proper requirements management you still have the time estimation problem.
It also didn't mention Evidence-Based Scheduling[1]. Also, the evidence-based-scheduling article doesn't mention points either.
[1]https://www.joelonsoftware.com/2007/10/26/evidence-based-sch...
However, in a large project, you can really only plan the beginning of the project this way. Eventually there are too many unknowns and you risk all the downsides of waterfall design. In my experience, a project like this has a burn down chart that goes UP over time (i.e. chunks are added faster than they are completed). This makes estimating the project impossible, especially if the chart is still concave-up (i.e. the rate at which it increases is increasing).
If you estimate large chunks, then you are less likely to add them over time, but you also won't be as good at estimating them. I think this is a good method for determining if a project is closer to a 1 year project or a 10 year project though. E.g. if you have 10 large equal chunks in a project and it ends up taking you 6 months to complete the first 1, you probably aren't going to finish by the end of the year, and you should evaluate if you are happy spending 5 years on it before you spend any more time.
i think? Anyone confirm/deny?
In fact if we were being honest with our managers we would be scandalized. We base our estimates on something like an 80% chance of getting something done (which already improves on the 50% chance by roughly doubling our estimate) and then every engineer I know has some informal rule about doubling or tripling the estimate before they hand it off to their manager. Those managers often add their own 20%. Then their managers see that something is up so they slash 50%. More than half of any project—perhaps even three quarters or more—is estimated as safety-factor. You would expect that if we were getting it wrong, we would be getting it wrong the other way, delivering early. The fact that we are late so often is a scandal in its own right. Adding more time buffer is clearly not helping much, since we have such a surfeit of it already. We must have wasted that safety buffer; there is no other explanation for how it disappeared.
And once you have set up these luxurious margins of safety it is already too late. Why is the engineer adding that extra factor 4x or whatever it is? It is because management is already at cross-purposes to engineering. That engineer is adding that safety because they do not feel safe without it. Any insufficiently safe ski-lift in active use will see hundreds of buggy ill-specified implementations of safety harnesses: I will go on this ride but I am taking some precautions.
The starting assumption has got to be that it is OK to fail on the deadline. This cannot be because of hidden information but must come as a result of trust: “we are eating into the safety buffer, that is totally OK and that is what it is there for, but I want to do whatever I can now to get you out of meetings and approach-planning and to fill out your timesheets for you and heck, even plan an amazing weekend between you and your fiancee to alleviate relationship stresses—and take any other distractions and loads off of your plate so that I can get your single-pointed focus on this feature and we can finish this.”
If management makes themselves that safety harness, then there is no cross-purpose.
Or conversely, stay in a boring-but-successful role too long at a company because they're able to play the game leisurely.
The problem is ultimately that the management buy-in opens management up to getting taken advantaged of. It's hard to balance accountability, when management via HR holds all the power. Peer reviews are rarely more than formality, used to reinforce the manager's personal assessment/feelings.
Or you just accept the research that people aren’t able to estimate time, and so it wasn’t a safety buffer on top of a real estimate so much as trying to compensate for the gut understanding that the estimate is pulled out of the air.
How likely is it that a surprise works in your favor? In my experience what you don't know rarely does. So my mental model is that completion times aren't normally distributed; they have a long tail. Additionally a task can't take negative time. This makes estimation tricky because a task can take much longer than the average. At my company we typically report an average and then explain why things took longer.
Which research would that be?