by rhlsthrm · 6y ago · 0 comments
The "really analytical" phase wasn't too crazy by HN standards:
- Break the complete project in Pivotal Tracker down to stories no larger than 8 points
- Track the time spent on each story in Harvest
- Use that data to figure out how much time a given point score equated to, along with variance.
- Work to reduce the variance.
I should also say...I've been estimating software for, good god, I haven't done this math lately, 18 fucking years. Do anything repeatedly that long, your instincts become pretty solid.