How many companies really plan for an event where their entire infrastructure goes offline and their entire team gets killed? Does even companies like Google plan for this kind of event?
Since 9/11, more than you might think. For example Empire Blue Cross Blue Shield [1] had its HQ in the WTC.
https://www.computerworld.com/article/2585046/empire-blue-[1... cross-it-group-undaunted-by-wtc-attack--anthrax-scare.html
And what a blast from the past:
> Some of the temporary locations, such as the W Hotel, required significant upgrades to their network infrastructure, Klepper said. "We're running a Gigabit Ethernet now here in the W Hotel,'' Klepper said, with a network connected to four T1 (1.54M bit/sec) circuits. That network supports the code development for a Web-based interface to the company's systems, which Klepper called "critical" to Empire's efforts to serve its customers. Despite the lost time and the lost code in the collapse of the World Trade Center towers, Klepper said, "we're going to get this done by the end of the year."
> Shevin Conway, Empire's chief technology officer, said that while the company lost about "10 days' worth" of source code, the entire object-oriented executable code survived, as it had been electronically transferred to the Staten Island data center.
But based on my experience, the initial recovery planning is the hard part. The documentation to tell a new team how to do it isn't so painful once the base plan exists, although you do need to think ahead to make sure somebody at your back-up vendor has an account with enough access to set up all the other accounts that will need to be created, including authorization to spend money to make it happen.
In some ways losing your ERP and it's backups would be harder to recover from than both sites burning down, insurance would cover that at least.
It's hearsay, but I was once told that achieving "black start" capability was a program that took many years and about a billion dollars. But they (probably) have it now.
It's most often referred to in the electricity sector, where bringing power up after a major regional blackout (think 2003 NE blackout) is extremely nontrivial, since the normal steps to turn on a power plant usually requires power: for example, operating valves in a hydro plant or blowers in a coal/gas/oil plant, synchronizing your generation with grid frequency, having something to consume the power; even operating the relays and circuit breakers to connect to the grid may require grid power.
The idea here is presumably that Google services have so many mutual dependencies that if everything were to go down, restarting would be nontrivial because every service would be blocked on starting up due to some other service not being available.
It's pretty much part of the basic day-to-day life in some industries.