It was expected to cost 3.3B€, but in the end will probably cost around 19B€.
Hoping for companies like NuScale, maybe they can get a continuous operation going and churn out cheaper and cheaper plants.
What has been learned at Flamanville that could be transferred elsewhere?
The gen 3 design is, depending on how you view it, 3 years old. It was found to be too expensive and too complex.
There exist new version of gen 3 reactors and there are design for gen 4 reactors, both claiming to solve many of the issues of the old gen 3 reactors.
However this is all assuming that Hinkley Point C stays in budget and on schedule, which would be a strange assumption to make given recent history.
So I'm not sure anything is being learned, or construction capability is increasing. Which is a shame, because that area of the world is the area with the strongest need for nuclear. The rest of the world will get by fine without it. And for that matter, it's likely that Northern Europe can build enough wind and storage to get around their need for nuclear. But it all would have been a lot easier if the nuclear industry was anywhere close to delivering on its lofty promises.