by a-walker · 4y ago · 0 comments
What's the difference between estimating and forecasting? Seems very binary as written, but at some point don't you have to look forward and make some assumptions on complexity/effort required to solve a problem and the general time it takes to solve them in order to do a forecast?
It’s running through simulations based on previous team behavior to give a range.
You can apply all the “science” you want, but at the bottom of it all you have engineers holding up a card with a “4” on it when the scrum dude says “add date picker to the Foo widget.”
If you estimate in properly calibrated 90 % intervals, you'll be correct 90 % of the time, and this is something you can verify continually.
I’ve always had issues when people are using hours instead of points. The one time we properly used points on a team it went really well.
This is really easy to practise and test too, since all you need are a bunch of questions where the answer is known, but you are uncertain of it. Then you can guess a range in which you are 90 % certain the true answer lies, and after 10 such questions, you should be correct roughly 9 times.
Points are a way to do this, but I prefer engineers who are calibrated. It's very powerful to ask someone for a calendar day when something will be done (or really just about any other question about anything), and be able to be reasonably confident in the span they respond with.