> Cost overruns at Vogtle and the cancellation of Summer [Nuclear Generating Station in South Carolina] led to Westinghouse's bankruptcy in 2017.
This raises a somewhat-scary question: in this case, Westinghouse's bankrupt remains were bought out by a private equity firm, and they presumably took on Westinghouse's obligations toward in-progress nuclear plant construction, but... what if that hadn't been the case? What if Westinghouse had just completely failed and ceased operations? Who would support the remainder of projects like Vogtle 3 & 4, and ongoing maintenance for the next however-many decades?
I guess a company in a heavily-regulated sector like this must have some sort of succession plan, but it's not clear to me how this would work, in the case of e.g. the company going bankrupt, and all the staff with institutional knowledge about a reactor design dispersing to various other companies. Hell, that could have even happened in Westinghouse's case.
For maintaining and decommissioning built plants, there are reserve and bonding requirements [1]. For new developments, that's a risk inherent to every construction project. Some hold that risk on their books, others sell it to an insurer. (One of the many reasons fuel is loaded last.)
[1] https://www.nrc.gov/reading-rm/doc-collections/cfr/part030/p...
Yes but I would argue that the level of risk involved is different between different energy options. $20B worth of solar and wind plus energy storage (including subsidies for home solar/storage and EVs with V2G capability) would carry less risk for this scenario than a single nuclear power plant.
I still think based on my back of the napkin calculations that solar + wind + storage (with the above mentioned subsidies) can be a compelling alternative to nuclear. It can be built faster, avoids the risk of a single large terrorist attack target, provides more energy independence for those who receive the subsidy for their own solar and storage, diversifies the grid, and avoids the need for a powerful government to control risky nuclear production facilities.
You can do a quick calculation and see that $10B of solar and $10B of storage will produce similar continuous base load power as the $20B Vogtle system.
In contrast, there is exactly one company that fully understands a particular nuclear reactor design. If that company disappears, it will take a lot of specialized knowledge transfer (likely requiring the continued employment of many of the original designers and builders) to allow another company or the government to take on that maintenance burden.
Still, I'm not convinced solar + wind + storage will come along soon enough at scale to eliminate enough fossil-fuel burning in order to dig us out of our climate change hole without things getting so much worse first. Then again, if it takes 16 years from permit application time to get a nuclear plant project completed in the US, maybe we're screwed either way.
We are, generally, pretty screwed though yes.
> *B. Dealing With Variability and Stability*
> Much of the resistance towards 100% Renewable Energy (RE) systems in the literature seems to come from the a-priori assumption that an energy system based on solar and wind is impossible since these energy sources are variable. Critics of 100% RE systems like to contrast solar and wind with ’firm’ energy sources like nuclear and fossil fuels (often combined with CCS) that bring their own storage. This is the key point made in some already mentioned reactions, such as those by Clack et al. [225], Trainer [226], Heard et al. [227] Jenkins et al. [228], and Caldeira et al. [275], [276].
> However, while it is true that keeping a system with variable sources stable is more complex, a range of strategies can be employed that are often ignored or underutilized in critical studies: oversizing solar and wind capacities; strengthening interconnections [68], [82], [132], [143], [277], [278]; demand response [279], [172], e.g. smart electric vehicles charging using delayed charging or delivering energy back to the electricity grid via vehicle-to-grid [181], [280]–[282]; storage (battery, compressed air, pumped hydro)[40]–[43], [46], [83], [140], [142], such as stationary batteries; sector coupling [16], [39], [90]–[92], [97], [132], [216], e.g. optimizing the interaction between electricity, heat, transport, and industry; power-to-X [39], [106], [134], [176], e.g. producing hydrogen at moments when there is abundant energy; et cetera. Using all these strategies effectively to mitigate variability is where much of the cutting-edge development of 100% RE scenarios takes place.
> With every iteration in the research and with every technological breakthrough in these areas, 100% RE systems become increasingly viable. Even former critics must admit that adding e-fuels through PtX makes 100% RE possible at costs similar to fossil fuels. These critics are still questioning whether 100% RE is the cheapest solution but no longer claim it would be unfeasible or prohibitively expensive. Variability, especially short term, has many mitigation options, and energy system studies are increasingly capturing these in their 100% RE scenarios.
Does it? And does this math scale?
Grid scale energy storage doesn't exist.
Also, consider that the second Vogtle class reactor will cost less and be faster to build, and the third even less and even faster... if they bought 50 of them, the cost per reactor would be pretty reasonable.
Solar power also benefits from economies of scale, but solar has already gotten much of the up front scale cost reduction, whereas modern nuclear hasn't even started yet.
If that fails, the government sometimes will setup its own company to take it in hand either at the state or federal level (this would almost certainly be federal).
Failing that, the projects would cease.
I guess there's still one failure mode: project is completed and plant is running, and then the manufacturer goes out of business. I guess in that case the government would have to act as a backstop no matter what, and worst-case they would just operate until the plant could be decommissioned.
Not to mention that Georgia has a multi billion dollar government budget surplus. Personally they should use that to keep power rates low. With the additional rate increases being requested by Georgia Power the citizens of Georgia are looking at a 40% rate increase in the next couple of years.
https://en.m.wikipedia.org/wiki/State_Nuclear_Power_Technolo...