by Reason077 · 3y ago · 0 comments
It's still generally true that the old grid infrastructure is re-used.
The UK has many closed coal, oil, gas, and nuclear power plants on or near the coast. When those plants are decommissioned or demolished, the grid infrastructure that was built for them (substations, transmission lines) is usually left intact.
New off-shore wind farms can now use those access points, which greatly reduces the cost of connection compared to having to build everything from scratch.
Over the last few years, lots of renewable generation and storage projects have taken advantage of the grid capacity in this area, but all the low hanging fruit is gone now.
These days, it is not usual for projects to be given a connection date in the 2030s due to the requirement to reinforce the transmission network.
E.g. to get a 132+ kV circuit constructed you need to go through the DCO/NSIP process which takes many years. https://en.wikipedia.org/wiki/Nationally_significant_infrast...
The CEGB constructed the 400 kV supergrid in the space of 15 years during the 60s and 70s. A project of such magnitude today would most likely be tied up in the planning consent process for 10+ years.
I agree, but also think that outside of the nimbys, other processes could be vastly improved.
There should not be 30 agencies involved, or even 5. There should be 1.
And that 1 agency can cover all of this, run all studies in parallel, and be a single contact point.
It should take days or weeks. Not months or years.
Modern cars are so good that any advancement is going to be incremental, and so it will take longer.
https://www.channel4.com/programmes/guy-martins-great-britis...
The old coal plants were built nearer to consumption, most of which is in the South East of England. The planned wind farms are mostly in the North Sea, far from South East of England. It will cost billions to build the infra to connect the north with the south. It’s not a simple matter of reusing what exists.
In the case of nuclear, this was to ensure reliable supply of cooling water. In the case of oil, it was to make it easy to unload crude directly off ships. The oil-fired plants were often co-located with oil refineries, many of which have now also closed.
I think that stable and sustainable utility supply would fall quite high on the priority list for most households.
(and small businesses; the recent price hikes have been far higher than a mere £50 and have been putting restaurants out of business)