by yladiz · 3y ago · 0 comments
It depends on how you're thinking about estimates. Just saying they're useless is arguably missing the benefit of the process.
Estimates are not generally useful in and of themselves (as in, the estimate value isn't particularly useful), but the process around agreeing on the value within a team is. If you're on a team and estimating a task during refinement, and there are wildly different estimates from the different team members, then the definition and/or understanding of the task is wrong and it needs more clarity and discussion. Another thing is that date estimates are problematic, and estimates should more generally be used to estimate complexity, and while they might be linked in some way, they're not the same.
The issue with estimates, in my opinion, comes down to the process after the value has been determined. If it's used as a benchmark or metric in some way, then you get into problematic situations.
I also do disagree with this:
> The reality is, unlike building a building, often the software being built has a ton of unknowable elements that are due to the software being bespoke in many crucial ways.
Honestly, software development is not as complex as people like to believe and there aren't as many unknowable elements as people like to think, and in my opinion this line of thinking is just an excuse to not actually think about what needs to be done to complete a task.
I would say if this is true in your work:
> Honestly, software development is not as complex as people like to believe and there aren't as many unknowable elements as people like to think, and in my opinion this line of thinking is just an excuse to not actually think about what needs to be done to complete a task.
You’re probably working on fairly rote easily producible stuff. That’s not a knock for sure - buildings are complex projects but are easily producible and rote, and contain some but not many unknowns. I imagine in modern times (I’ve not tried to do it for about 25 years tho, and it definitely was complex then!) making modern websites and e-commerce stuff is fairly rote and predictable and mostly a design process.
Developing something innovative is full of unknowns that can only be determined by trying to do it. Building arbitrary scale SaaS data services, complex cryptographic platforms, more recently AI stuff, all are replete with unknowns. Developing complex business systems as well.
I see your point, but I would argue that estimates are more valuable than just discussing the task because they give you a shared language to quickly define how complex you think a task is, and can also help avoid getting too into the weeds about specific implementation details when talking about the task in general. There are definitely problems that can arise from estimation, but if you're able to avoid them, it can be a useful tool for a high functioning team.
The problem comes when you string estimates together and compound the mistake by assuming a precise estimate is an accurate one. I generally refuse to give precise estimates for that reason.
I think we can all agree that the vast majority of software work does not belong to the categories above, and is therefore relatively predictable.
I’m sure we can disagree here, but I would note we don’t all agree.
And it's the hardest part to estimate. To make estimates you must first get the requirements clear, but that's a major part of what you were trying to estimate.
Funny, I've been hearing this constantly over the 24 years of my professional experience as a software developer and I've yet to see it proven true.
Unless we're talking about toy examples like Hello World, developing quality software is devilishly complicated and, in my opinion, downplaying this complexity as an "excuse" is in itself an excuse to compromise quality.
EDIT: Fixed a few words my phone auto-"corrected" for me.