by throwaway2037 · 2y ago · 0 comments
I checked the Wiki page: https://en.wikipedia.org/wiki/Vogtle_Electric_Generating_Pla...
> Two additional units utilizing Westinghouse AP1000 reactors were under construction since 2009, with Unit 3 being completed in July 2023.[9][10][11] This last report blames the latest increase in costs on the contractor not completing work as scheduled. Another complicating factor in the construction process is the bankruptcy of Westinghouse in 2017.[12] In 2018 costs were estimated to be about $25 billion.[13] By 2021 they were estimated to be over $28.5 billion.[14] In 2023 costs had increased to $34 billion, with work still to be completed on Vogtle 4.[15]
Those numbers are simply mind blowing. Why are these still built? How much solar/wind/battery capacity can 34B USD buy!?
I feel the same about the two big nuke projects in the UK (Hinkley Point C & Sizewell C). It makes no sense compared to solar/wind/battery.
According to How Big Things Get Done, at least 30B worth. Nuclear plants have some of the worst cost and time overruns for large projects, wind and solar some of the lowest (beaten only by roads).
And his theory as to why this happens, is that wind, solar, and roads are self-similar. Building the first 10% directly informs you on how to build the next 10%. Everything you learn along the way can be rolled back into the project in a feedback loop.
What you learn shingling a roof or building a nuclear reactor doesn't help this project all that much. It helps the next. And how many nuclear reactors does one worker build in their lifetime? 2? 4? That's not a lot of opportunity for process improvement.
> Plant Vogtle proceeded with no cost-cap, no consumer protections, and Public Service Commission (PSC) staff were prohibited from conducting analysis comparing the costs of nuclear to clean energy alternatives.
https://www.powermag.com/blog/plant-vogtle-not-a-star-but-a-...
At the other pair of reactors started at the same time and with the same design in Soith Carolina, executives are in jail for lying about the project. The SC reactors were also abandoned.
Nuclear in the US is so expensive that even starting a new reactor requires considerable corruption.
Best line I've come across in a while. I'm gonna use it. Is it yours?
And reactors are inherently too big and complicated. A wind farm, solar farm, or a road is intrinsically much simpler.
And reactors will suffer from decision makers sitting around a table and changing designs for the next one because engineers have thought up new failure modes of the last design and nobody wants to be the person who says "no" and then has a failure. Along with the natural tendency of US management to increase the spending of their departments in order to increase the size of their own personal kingdom. You'll never manage to stamp out reactor after reactor all of the same design.
France built 58 over 20 years, that's how you make it economical. India says they want to do one a year IIRC, which is probably good enough too.
https://phys.org/news/2021-03-trillions-hidden-energy-extern...
What's interesting is that they mentioned the externalities for geothermal are very very low.
This is cherry picking. Look at the 10 years, or even lifetime, average availability. It's 90 or 95%. The reason for this bad number is because of delayed maintenance due to COVID.
> "serious consequences for power plant cooling systems, as the drought reduced the amount of river water available for cooling."
The reduction of power output of French nuclear was something like 0.30%. You read that right. So I would call "serious consequences" a blatant lie.
Not without caveats though. Humans are shit at statistics. Their sense of the aggregate danger of putting 100 'safe' items in close proximity often underestimates the odds by half, and in some cases by an order of magnitude.
You might get lucky and lose two personal hard drives in your entire life, but the IT guy managing 100 drives is dealing with failed drives 'all the time'. Backblaze reports on something like 10,000 drives and they are claiming something on the order of 200-300 failures. And I think that's per quarter, not per year.
What do you do with an array of reactors where one right in the middle did not fail cleanly?
I'm not much of a fan of nuclear (pun not intended?) and would like to see solar + wind (+ other renewables) cover most of the load. But if enough resources were pooled to design an SMR, with extensive safety studies, lifetime planning, involvement of multiple parties (e.g. scientific and engineering teams from different world states) - I don't think I could really oppose, especially given the global warming situation.
Of course - there's "ideal nuclear" and there's real existing nuclear, which is quite different and often very problematic.
They absorb more indirect light, but the main advantage is that hot panels drop in efficiency, and standing them up improves heat dissipation substantially.
One of the bits that stood out to me is that it has an output curve that partially lines up with The Duck, because you get a period of low-angle exposure near sunset. I suspect you get quite a drop at high noon, but that's fine as long as not all solar panels in the grid are vertical.
As a point of comparison, the Large Hadron collider had a $9 billion budget, and that required a 27 kilometer circle to be dug.
Costs are related to the assurance of safety through careful documentation and processes beginning with regulation and insurance underwriting of design engineering, construction, operations, and maintenance. This sort of thing only makes sense to do so at large scale to make it economical. Scale also has its costs. Safety isn't something that can be Boeing'ed because the NRC can and will shut the whole thing down if it were to be found unsafe.
Renewables are far cheaper, and can be built much more quickly. But there is an argument for (some) nuclear around energy security and diversification of supply. Batteries are great but can't really provide long-term storage (ie: multiple days/weeks). Do we want to rely solely on natural gas as a backup during the cold, calm, winter weather patterns which in some years can persist for weeks? Last year's energy crisis suggests maybe not. Or can we build enough interconnections and rely on imports from our neighbours?
Also worth considering that Hinkley Point C & Sizewell C are really only replacing existing nuclear plants that are shutting down. Even if both are built, the UK will still have only around half the nuclear capacity in the 2030s that we had in the 1990s.
I'm guessing because there was no step in the process where it seemed like a better idea to stop construction and have spent whatever costs so far to get nothing of value, rather than accept the cost increase and end up with high availability, somewhat dispatchable generation.
There's not a lot of new projects in nuclear, because construction costs are high and subject to cost overruns as projects get delayed, and delays seem inevitable. That's why there's all the talk of modular nuclear and what not. If it was feasible to build these plants on time and on budget, the generation parameters are good --- doesn't use much fuel, tends to be available outside of scheduled maintenance, can modulate generation to follow demand, if the economics make sense (as-is, most of the plant expenses are fixed cost, so you may as well generate as much as you can to amortize the cost over more kWh)
For the cost of batteries, NREL published this review of reviews, and lands at ~480/kWh of capacity:
https://www.nrel.gov/docs/fy23osti/85332.pdf
So split the $35B (there's a recent $3B that hasn't made it wikipedia, as I understand it) half and half, and you get 17GW of solar, and 36GWh of storage.
As far as translating this into per-kWh costs, most estimates I have seen put Vogtle at $0.17-$0.18/kWh. The equivalent for solar is $0.04/kWh. To charge a battery with that same solar, and then deliver it later, it's $0.13/kWh, when doing the napkin math with those NREL numbers up there.
Batteries until today are not a viable solution.
When talking about the electrical grid you have to be able to generate energy in any amount whenever you want.
"Any unexpected sudden disconnect of the NPP from an otherwise stable electric grid could trigger a severe imbalance between power generation and consumption causing a sudden reduction in grid frequency and voltage. This could even cascade into the collapse of the grid if additional power sources are not connected to the grid in time."
Basically NPPs are designed to SCRAM for all sorts of reasons, then the sudden loss of multiple GW really ruins the grid managers' day. The first paragraphs of [1] make it clear that a large, stable, grid is a pre-requisite for NPPs not a result of NPPs.
[1] https://www.iaea.org/sites/default/files/gc/gc53inf-3-att5_e...
I think there is an error thinking this way.
It is like saying "everyone must own a pickup truck, because they must be able to move any household appliance or furniture item at any time."
"nobody can drive an electric vehicle because they must be able to drive to the next state at any time."
Honestly, you can have a very reliable electrical grid that is runs on solar/wind/batteries for most of the time.
Batteries enhance the grid, and if there was a period of no wind or no sun, it is quite easy to spin up gas turbines for a day or a month.
Could we all live a different way, communally instead of in our own big boxes? It's physically possible but socially impossible. The truth is we'd rather burn the planet to the ground and we will. That's our nature, little use fighting it.
Not exactly. It is possible to manage the demand side to some degree.
For example, Octopus Energy in the UK has a "Intelligent Octopus Go" contract which offers much cheaper night rates, in exchange for giving up control over when and at what rate your EV charges. You just tell them what battery percentage you need by what time in the morning. They plan the charging within this constraint and get paid by the grid operator to balance the grid.
Another example are dynamically priced contracts where the prices vary hour by hour based on the day-ahead market prices. I have such a contract and I charge my EV only during the cheapest hours when other demand is low. Sometimes I postpone charging for a day or more because I have sufficient charge for my needs and I expect lower prices later, e.g. based on weather or upcoming weekend.
This isn't true. Demand is predictable to some degree on multiple timescales.
But if it was true, why would that help nuclear? It is most suited to the role of producing a set amount of power continuously.
Why are so many people fans of this mythical nuclear power they've invented inside their own head? (or had fed to them)?
It all just seems like lazy, second-hand, anti-renewable propaganda.
Windturbines are rated for 20+ and can be extended.. current generation are usally changed as there are bigger models available, with higher profit margins
That seems very far fetched
I'm guessing you'd run into space constraints pretty quickly. For one large project a nuclear reactor is incredibly compact compared to most alternatives except maybe hydro.
https://www.statista.com/statistics/1305820/longest-power-tr...