Very very little is made/manufactured on site. You do not make turbines, computers, pipes, or much at all, on a construction site. You form, weld, pour, and assemble. The goal would be a standard design, to cut those giant engineering and custom fabrication costs to a small fraction.
You don't need to deliver a completed factory on a pallet to save costs (although that's possible with distributed small module reactors, as Asia is ramping up for).
The costs of the French nuclear scale-up: A case of negative learning by doing
https://www.sciencedirect.com/science/article/abs/pii/S03014...
"Conversely, the gradual erosion of EDF’s determination to standardize (caving in to proposals of numerous design changes in the wake of the ‘‘frenchifying’’ of the Westinghouse de- sign—the P’4 reactor series—and above all to the new N4 reactor design pushed by the CEA), as well as the abrupt slowdown of the expansion program after 1981, paved the way towards a gradual demise of the French success model, as borne out in lengthened construction times and ever higher cost escalation towards the end of the program (cf. Section 4 below)."
https://endexiresearch.wordpress.com/wp-content/uploads/2020...
The entire nuclear industry (construction, operation, support) cost France € 228 billion and produce 11000 TWh (by 2012). That's 2,07 cents/kWh. Not too shabby.
All nuclear power plants made since around 1980s or so have been made in factories. The US (and other nations) use them all the time for their submarines- defense concerns correctly override environmentalists (and the oil companies backing them financially).
The problem is a solved one. We're rich enough to afford to tilt at windmills instead- for now, anyway.
They can now, see Small Modular Reactors (SMR).
1. Build prototype
2. Iterate on prototype.
3. In conjunction start standardizing and automating processes.
4. Achieve large enough scale to amortize the factory and process optimization costs over enough units to actually gain anything.
The “SMR hype industry” seems to be perpetually stuck at 1, not even being able to deliver a single prototype.
All the while talking like the factory already exists and SMRs are solved.
Somehow it doesn’t add up.
I don't know, I'm not a specialist. But this came up by doing a rudimentary search.
KLT-40S Russia
HTR-PM China
HTR-10 China
HTTR Japan
"Super safe bank"
"Really clean hamburger restaurant"
"Most trustworth car salesman"
"Very accurate surgeon"