[0] https://www.amd.com/en/products/processors/server/epyc/7003-...
[1] I couldn't find 14TB enterprise SSDs on Intel's website, so I'm using the numbers from 6.4TB drives: https://ark.intel.com/content/www/us/en/ark/products/202708/...
[2] I'm not sure offhand which model number to use, but both models that support 200GbE on page 93-96 have this maximum wattage: https://docs.nvidia.com/nvidia-connectx-6-dx-ethernet-adapte...
Or, you can skip all the hand calculations and just fiddle with Dell's website to put together an order for a rack while trying to mirror the specs as closely as possible (I only included two NICs, since it complained that the configuration didn't have enough low-profile PCIe slots for four):
https://www.dell.com/en-us/shop/dell-poweredge-servers/power...
In this case, I selected a 1100W power supply and it's still yelling at me that it's not enough; 1400W is enough to make that nag go away.
That said, being able to do 800G in an 800W footprint doesn't automatically mean that you can drive 100G in a 100W footprint. Not every ISP needs that 800G footprint, so being able to deploy smaller nodes can be an advantage.
Also: I was assuming that 100W was the whole package (which is super impressive if so), since the Netflix serving model should have most of the SSDs in standby most of the time, and so you're allowed to cheat a little bit in terms of actual power draw vs max rating of the system.