142 points · by bilekas · 1y ago · 89 comments
They will be HUMONGOUS because they need a large surface to radiate away the heat for the passive safety, so they can't be easily put into a containment building.
A core of a PWR plant is _tiny_ for the amount of power it produces (around 3GWt!), just around 5 meters in diameter and 15 meters in height.
The pebble bed reactor in the article (HTR-PM) is around the same size, but it produces a mere 0.25 GWt.
Pebbles themselves are also problematic, they tend to swell, crack, and they can't be reprocessed using the current technologies. They MASSIVELY increase the amount of waste.
Still, this is a good price to pay for getting a meltdown-proof reactor.
> Pebbles themselves are also problematic, they tend to swell, crack, and they can't be reprocessed using the current technologies.
It is simply not true that pebbles tend to swell and crack. Quite the opposite happens: fuel elements in the current generation PWRs tend to swell, crack and burst. This happens because some fission products and decay products are gasses, such as xenon, kripton, radon. They build up in time and create internal pressure. The same happens inside the fuel kernels in the pebbles used in this reactor, but those kernels are specially built to withstand much higher internal pressures.
Here's a relevant quote from [2]:
> As the pressure vessel size is reduced, the more efficient spherical geometry can be adopted, and the required wall thickness drops dramatically to the point that a 35 μm SiC layer can indefinitely contain gas pressures in excess of 100 MPa. This compares to the main reactor steel pressure vessel which may go as high as 20MPa or the Zircalloy cladding which can have pressures up to 10s of MPa in limited conditions – temperatures far below what the ceramic pressure vessel tolerate
As for the reprocessing part, I think you are jumping the gun. There is no reprocessing done in the US, at all, for any type of fuel. Even where reprocessing happens, as in France, the benefit is quite reduced. One can extract some plutonium and unburned uranium, but in the end that will allow you to extract maybe 10-20% more energy from the original amount of natural uranium. It will not make you extract one hundred, or 10 times, or even just twice as much energy. Reprocessing is simply not a game changer. It is not clear at all if it makes economic sense to build the highly complex facilities that do reprocessing, for the limited benefit.[1] https://aris.iaea.org/publications/SMR_catalogue_2024.pdf
The problem is that if the pebbles aren't reprocessed, you now have to store their very large volume. The moderator, graphite, is integrated into them. This is unlike a LWR, where the moderator is water that the spent fuel can be simply lifted out of (after cooling). LWR fuel can be stored after a few years into dry casks; the equivalent for pebbles would be vastly larger and more expensive, and involves storing the spent fuel with its moderator, increasing concerns of criticality (although I imagine they'd be doused with borate or something to prevent that).
Thickness of a pressure vessel wall is proportional to pressure x linear dimensions of the pressure vessel, increasing at a given pressure as the vessel is scaled up.
I held their stock for a while until I realized they don’t exist to make a reactor. They exist to get funding.
Sounds crazy, but look through their actions. All press releases are just talk about what they will research and with whom they talked or made a “memorandum of understanding”. The CEO CV is also interesting since it lists a whole lot of board positions and titles but it’s not clear what he has actually done.
I picked NuScale because it's a PWR SMR, and is the only SMR design that was approved by the Nuclear Regulatory Commission. HTR-PM is an SMR, and comparing it with a full scale PWR reactor is not entirely fair, because reactors benefit from the square-cube law: the larger a reactor is the more efficient its neutron economy is, so you can extract more power per unit of volume.
As for NuScale being a scam, it would be probably the most elaborate scam in the history of financial scams. They were founded in 2007 and went public in 2022. People don't spend 15 years to run a scam, especially if this involves not one by two government agencies (the NRC and the SEC). There's a huge probability that such a scam would not work in the end, with an additional likelihood that you get relocated to a correctional facility (see Elizabeth Holmes).
It's more.
> while NuScale has a volume of 101 m3 and yields 77 MWe
VVER1200 has the inner vessel _diameter_ of 4.2m, height of 11m for the internal volume of 153m^3, and 1200MWe capacity (so around 3GWt).
_THIS_ is what you're comparing it with.
> Quite the opposite happens: fuel elements in the current generation PWRs tend to swell, crack and burst
Nope. A swollen or a ruptured fuel rod in a regular reactor is a reason for SCRAM. The water inside the reactor vessel is constantly monitored for fission products. The individual fuel tablets swell, but they are contained inside zirconium rods.
No, we're looking at a core the size of a small residential tower. Probably around 30 meters in height.
One of Germany's PBRs had to filled with concrete after it was defueled, they couldn't decontaminate it enough to dismantle it.
If you just need 250MW of power, then just use electricity sourced from a regular PWR for heating. It'll be cheaper.
Waste heat can be useful for district heating systems because houses don’t need to reach high temperatures, but few designs give you access to even 300C and nothing currently hits 1,000+C.
Using helium indicates a problem with kinematic viscosity of cooling gases? Nitrogen would be non-reactive enough, I assume?
Nitrogen will undergo an (n-p) reaction to produce carbon-14 which has a half-life of 5700 years.
That's wrong, Hamm-Uentrop was a full scale commercial reactor. It did run in total for a week or so between 1985 and 1989 and was then shut down. The fundamental problem is, that the pebbles grind against each other, and being of the same material as pebbles they can grind each other down. (Now if you wonder why this wasn't discovered at the experimental reactor in Juellich, those guys just never mentioned that they lost fuel.)
This video explores an incident with a reactor of a similar design, and very rudimentarily explains the way pebbles and the helium gas is used.
There’s of course 2 flavors of HTGR (prismatic and pebble bed), and people choose the pebble version for continuous refueling despite all the drawbacks [1]. But there’s a lot of reasons to do prismatic. Can’t wait to see China’s prismatic HTGR.
Did the pebble-bed reactor's "commercial-scale inherent safety" also pass a test with an compromised container, which would admit air that would cause the graphite to burn?
Rats, then it would cause about as many deaths per GWh as the coal it's replacing.
Not in the real world. We're deploying solar and wind as quickly as we can because they're the cheapest sources of power. The bottlenecks are production and permitting, and there is no indication either of those are seeing a step change in the next decade.
There is a reason America and Europe, where anti-nuclear sentiment runs ripe, are building gas power plants and infrastructure at the fastest clip in history. In the West, the choice is gas or nukes. In the China and India, it's coal or nukes.
Summary: As the temperature rises, neutron absorption increases, reducing fission and thus temperature.
Negative fuel temperature coefficient is not an unusual feature.
The real question is whether the heat removal system of the reactor as a whole is sufficient to remove the decay heat to keep the fuel within the limits.
Because the real problem with solid rods is that they ... are solid rods, and if they start "overreacting" you can't split up the rods, unlike a pile of pebbles/spheres.
Modern PWRs also have this safety feature, if a core melts down, the molten mass will be contained in a core catcher. Where it'll be mixed with inert material that can provide enough surface area and thermal mass to prevent further fuel mass migration.
The biggest problem in the core catcher design was to make sure that the molten fuel lava spreads out enough for the passive cooling to stop it from melting through concrete.
Pebble bed reactors will have a similar problem. You can "drain" pebble beds somewhere, but then you need to make sure that this "somewhere" can conduct away the decay heat without melting.
You're saying LFTRs can't have a pool of cooling liquid that the overheating fuel liquid can't mix with and cool down even faster than solid rods?
So how could LFTR safety plug and cooling pool be a fairy tale?
> The pebble-bed reactor is designed so that this effect is relatively strong, inherent to the design, and does not depend on moving parts. This negative feedback creates passive control of the reaction process.
From the Wikipedia article on the PBR that was linked in a neighbouring comment.
It should, at least if built correctly, be impossible for it to get into a run-away state. Even if it lost all power, and everyone walked away, it should not melt down.
Amazing. Well done! How far this country has come in the last few decades is nothing short of breathtaking.