by jph · 11mo ago · 0 comments
When teams do need strong estimates, then the best way I know is doing a project management ROPE estimate, which uses multiple perspectives to improve the planning.
https://github.com/SixArm/project-management-rope-estimate
R = Realistic estimate. This is based on work being typical, reasonable, plausible, and usual.
O = Optimistic estimate. This is based on work turning out to be notably easy, or fast, or lucky.
P = Pessimistic estimate. This is based on work turning out to be notably hard, or slow, or unlucky.
E = Equilibristic estimate. This is based on success as 50% likely such as for critical chains and simulations.
I've found giving probabalistic estimates to be hopeless to effectively communicate, even if you assume the possible outcomes are normally distributed, which they aren't.
Wikipedia: "The justification for using the 50% estimates is that half of the tasks will finish early and half will finish late, so that the variance over the course of the project should be zero... Because task duration has been planned at the 50% probability duration, there is pressure on resources to complete critical chain tasks as quickly as possible, overcoming student's syndrome and Parkinson's Law."
https://en.wikipedia.org/wiki/Three-point_estimation
https://projectmanagementacademy.net/resources/blog/a-three-...
And yeah, they can be useful when you can must put numbers to things and can decompose the work into familiar enough tasks that your estimation points are informed and plausible. Unfortunately, in a field often chasing originality/innovation, with tools that turn over far too often, that can be a near-impossible criteria to meet.
BTW the SixArm name and ROPE is merely my personal work. Way back when, I had to put on the trademark because someone else said my work was theirs.
Each stakeholder gets the kind of fortune they want. The important aspect (to me) is that the four viewpoints show all the stakeholders that their viewpoints are quite different.