The average data centre is 10,000 square metres (2.5 acres).
As well as compute and network facilities, DCs also need to accommodate parking, personnel areas, cooling, fire-suppression, power substations, power redundancy (generators), ground-security…
244 acres is absolutely at the upper end of any DC site.
https://www.theverge.com/ai-artificial-intelligence/933687/u...
Most hyperscalers now prefer to build larger sites as “campuses” which may consist of many buildings each consuming 40-100MW, and then yes each building needs most of what you mentioned, so it adds up.
A few sites are now also contemplating BTM or ‘behind the meter’ power generation which takes additional space.
Then some sites like Microsoft’s Fairwater design are optimized for a very large number of Accelerator cabinets — think GPU, TPU, etc. Those cabinets are each consuming 140kW today and with a path to 700-1000kW cabinets soon, so that’s one super dense building instead of a campus of less dense buildings filled with Compute.
So far it seems to be more of a concept of a plan. I wouldn’t be surprised if they build smaller scale data centers first, then cancel the 40000 acres expansion. That sorts of feel like a marketing tactic. If not and they are serious, are we close to peak bubble?
Storage? Even that is now ultra-compact.
Figure on ~10 million square feet of conditioned DC space per year, approximately 5-10GW of additional power consumption to power those 250k cabinets (depending on the exact mixture of what’s in the racks — Compute, Storage, Network, Accelerators), and that’s just for one hyperscaler.
There are at least 5-7 companies in the hyperscaler weight class although likely none individually meaningfully larger than AWS, they’re the 800lb bear and everyone else is in the 500-750lb range.
It’s a lot. Datacenters also take long enough to build that a hyperscaler is pouring concrete today for shells they expect to serve real workloads in 2029 - 2031. What you’re seeing come online today in response to customer demand really started being built in 2021 - 2023.
TIL.
400 vaticans
Datacenters aren’t built next to Nordstrom. Theres just no reason to spend on engineering and construction that increases density like underground parking.