There is no free gas pipeline capacity to get gas out of West Texas. Any time new pipelines are built, they are filled within months.
This makes a ton of sense for oil producers (which are also gas producers) who can sell their gas for less of a loss (potentially a profit!) and also for MSFT who can lock in long term contracts for minimal cost. I'd guess these contracts are for $1-2/MCF which is win/win for the oil companies in the area and MSFT.
Further, there's a gas turbine shortage so Microsoft choosing to put their (presumably limited) allocation of gas turbines in West Texas, where they have good alternatives, seems a bit mysterious. Why not save that massive amount of turbines for the northeast DCs, where renewables work far poorer yet gas is more reliable?
The reasons that seem most convincing to me:
1. Political environment is hostile to renewables and Microsoft doesn't want to paint a target on their back by choosing solar plus batteries, the choice others are making in West Texas.
2. Grid connection drastically changes economics, but pipelines for gas are cheap or something, so the massive cost and delay from grid interconnection simply isn't worth it
3. There are particular political favors going on with Chevron, e.g. Chevron wants gas in the area and is willing to increase MS's turbine allocation if they do it in west Texas, or Chevron is helping get around pesky local political approvals for data centers, or something like that.
The cost of gas does not seem like a justification for this, though.
With enough batteries they might get through the night, but seasonal shortages are much harder to handle that way.
I bet a carbon tax on data centers would be popular if the Democrats get back in.
Put another way if you want to store power say 1GWh for the worst month, well a solar panel provides a lot of power over even the worst month. 20MW of solar panel averaging even 40MWh/day * 30 days = 1.2GWh and cost way less than 1GWh of batteries.
Near the arctic circle Wind fill the same niche.
What do you mean? Long periods of calm weather during cold temperatures is not unheard of in Finland and does cause issues at times due to amount of wind energy that has been built in recent times.
That can help on overcast days, or the middle of winter when days are shorter, but you still need battery capacity to run for stretches when there is no sun producing energy.
For residential its often recommended to have 3 days of storage capacity + the option for a backup generator. I'm not sure what the recommendation is for industrial projects, but I expect they would still need a backup generator. If they already have to put in a generator to handle the full load of the server farm, and they have cheap local gas, why bother with the solar? At a minimum you have both, but the generator (or power from a contracted gap generator) is a given.
Given the state of the power grid in Texas, this could be the most important consideration. Why? Texas is not connected to the national power grid, and only electricity from plants operating in Texas is available. The last winter and summer, demands on the grid have severely stressed, as reported in many places. In 2021 there as a state-wide crisis and almost a complete failure. https://en.wikipedia.org/wiki/2021_Texas_power_crisis
In short, you're going to have to build your own power plant anyway, so why bother with the grid? Gas is the cheapest, fastest zero-to-production choice for onsite power generation, and has been for a long time. Unless you're dealing with nuclear, the fuel cost just doesn't matter compared to the rest of the buildout, and gas wins because you can take off-the-shelf turbines and bolt them down.
You can only get away with it in places that don't care about environmental regulations, which are the places most likely to approve new buildout of gas infrastructure anyway. Nobody in the northeast is going to approve the creation of a brand new carcinogen factory.
Is it, though? There's a ton of projects out there waiting to get their solar on the grid in west Texas, partnering with one of them and launching the project early while waiting on the interconnection queue, and adding enough batteries, gives a more robust solution right now without the SPOF nature of large single generators.
Add to that the long backorder list for gas turbines right now, with no end in sight, and I'm surprised that Microsoft would power this particular location with turbines because it's probably their best chance to do off-grid massive solar projects.
Massive off-grid solar is what China is choosing for some absolutely massive new industrial projects. Nuclear is a no-go because it takes so long to deploy, but solar + batteries are cheap COTS and available in abundance, unlike gas turbines.
Yes.
There is no point in waiting for interconnection when you can just... not do that, and do all your generation behind the meter, with complete control of the generation to match your load. Solar wants an interconnect so they can sell off surplus; with gas you just turn the dial down to meet the load and walk away.
The clock is running on the datacenter goldrush. 70-90% of the capex window is going to be soaked up just with construction time. Introducing a capricious ERCOT permit process and shopping around for friendly solar projects to hop in bed with makes no sense when you can just write a check and solve the problem forever.
I'd bet the deal with Chevron was to enable Microsoft to hop the queue here and get those GEV turbines soonest.
gas turbines run at night too so there's no storage/backup supply issue to consider. They also take up significantly less space than wind or solar and those data centers are already gigantic.
When you can colocate across the street from someone who's otherwise paying to get rid of it is.
When the fuel is free-ish who cares about backorder on turbines. You can run big diesels on NG (just like the pipeline people do).
If you want power quickly, wind, solar, and battery can be planned, installed, and producing power within a couple of years. Nothing else comes close to being that quick. If you want power this decade, that's pretty much the only thing available.
Respectfully, the laws of NPV and IRR hurdles don't matter in Chinese infrastructure.
Whatever you choose in the US, it's not cheap, and developers crawl over each other to sign up hyperscalers. Race to the bottom.
If demand > supply then the price goes up. Doesn't mean you can't buy something though.
Last I heard the wait time for turbines was ~5 years at the moment. I'm sure MSFT has some inside baseball with Chevron but it doesn't work as a general rule of thumb.
To sell excess back to the grid when funny things happen to texans in the winter?
Oy vey, what a perverse incentive.
Cheap gas is great, but 2.67GW of new build natural gas in this market will cost $6-8 billion in fixed costs. You need wholesale pricing of ~$50-60/MWh ... OVER 25 years! ... to recover just the fixed costs.
For West Texas, prices averaged mid-$30s over the last year.
Microsoft has all of the leverage here, and Chevron wants a big announcement in an area where they don't have a lot of experience.
This won't apply to every datacenter, but the AI inference ones especially, should be seeing most demand during the day. So what's built in north America is used when it's daylight there?
If so, isn't that a perfect case for solar?
To be clear, I'm not saying it can power down, but at night it should be able to scale down significantly?
I don't know if this is necessarily true - latency isn't really important for inference in the same way as many other services (at least the max ~300ms latency you get from hitting something on the other side of the globe) - compute in NA can serve all the other timezones just fine.
Demand for AI is global (except for Anthropic, haha).
When you build a DC that works only when the sun is shining, you are wasting half of you GPU capacity
Texas is going to be somewhat shielded from this because of US policy on this front. But probably only for a few short years. Mostly LNG exports are currently very lucrative. But LNG production is bottlenecked on expensive infrastructure and shipping. And of course lots of importers of LNG are looking for more affordable alternatives as well because it is expensive. Doubly so since the recent Gulf conflict. A lot of planned infrastructure expansion just got cancelled.
So, there's probably a bit of gas overproduction happening in Texas currently and that's going to cause predictable issues when demand is going to be structurally lower. And the double whammy of petrol/diesel also going into structural decline is going to leave Texas with a lot of over production.