It is almost universally recognized as good to do exactly that. It's better to have one planned extra trip to return excess materials (if they can't be used on the next job) than to have multiple unplanned trips when you unexpectedly run out of this or that.
One of my uncles asked why I’m budgeting for an extra $150 of material we won’t need. I asked him how much it would cost to get us all up here for another weekend to finish if we needed extra parts. The answer was “more than $150” and he understood.
It’s even more crucial to keep enough material on the jobsite when you’re running a project and paying $140 an hour for an electrician.
(Turns out the line to the gauge was borked, so it never turned off the pump, so the pressure built until it busted my pipes.)