by _n_b_ · 4mo ago · 0 comments
1. (Design) Building floorplate and architectural complexity (i.e., divergence from 'big box')
2. (Construction) Schedule adherence. Almost any one-off expense to stick to the schedule is worth it, but to your point, these are often challenged or delayed. Building and testing equipment on skids off-site is almost always worth it.
3. (Design/Commissioning) Schedule adherence. For commissioning this is typically driven by design choices (did you pick a high-TRL process, or if not, do all the work required to mature it in parallel to construction?) and by building the right commissioning team (knows their job, knows the plant).
If more expensive plant & equipment gets you ahead on any of these 3, 99% of the time that is an overall optimisation.
The net result, we topped out and roofed the big house, then built the small house in its entirety while the owners of the big house chose their windows. Add that in favour of waterfall design...
I've never worked in this field as the GP, but I have family that do and I've heard plenty of stories and made my own observations, but definitely take my two cents with plenty of salt. Maybe GP will reply also.