Not Texas and Arizona. Why?
The reason Texas is experiencing a boom in data centers is friendlier power grid policies to data centers (similar to why Google is building in Finland), in combination with (relatively small) tax incentives.
When Finland contracted with France to build their latest reactor, they wisely had a fixed price contract where the French company would pay for const overruns. At groundbreaking in 2005, they planned for a 2009 completion. In 2016 it bankrupted Areva, with the French government owned EDG saving parts of the company crucial to the nation. It wasn't completed u tip 2023:
https://www.helsinkitimes.fi/finland/finland-news/domestic/2...
When the US last decided to build nuclear, Westinghouse AP1000s, two in South Carolina and two in Georgia, it resulted in the bankruptcy on Westinghouse, putting all of Toshiba, its owner, at risk:
https://www.csis.org/analysis/westinghouses-bankruptcy-and-i...
The two South Carolina reactors were abandoned at the cost of a substantial fraction of the build cost, in the billions, and utility executives went to jail for deception about it. Georgia finished its two reactors, but only by creating some of the most expensive electricity out there today.
Storage and renewables are cheaper, faster to deploy, and work really really really well in Texas and Arizona. Despite nearly free natural gas in Texas due its state as a by-product of oil extraction, most of the new electricity grid assets in Texas are wind, storage, and solar, and that's independent third party investors making those choice in the grid to make money, as Texas has perhaps the "freest" electricity market in the United States when it comes to who is allowed to build grid assets and make money off them.
If the far north places have hydro that's already built and not being used, that makes sense for data centers. But new nuclear is not a serious technology, it exists mostly based on vibes.
It seems to me the main problem is we build so little of it that we don't have the people, skills, supply chains etc to do it well. China generally builds it's reactors on schedule and within budget.
On time, yes, because China is great at construction. On budget, almost certainly, but we have very little visibility into true costs. China's labor costs are getting far higher as it becomes richer, and there's a good chance that it will reach a state of higher economic development where its costs for nuclear mirror those high costs in present day France.
And even with all that their total share of nuclear is declining y/&y and projected to continue to decline. Because it’s still too expensive even for a autocracy
Unfortunately, the project was cancelled for moronic political reasons.
https://en.wikipedia.org/wiki/Chernobyl_Nuclear_Power_Plant_...
Well, avoiding business deals with that neighbor is the only rational action. Building a Russian nuclear reactor as one of their neighbors is suicidally stupid. At least go to South Korea instead.
The US is also finding out that when it threatens its neighbors and allies that it will lose out on crucial industrial deals, such as Canada and Europe moving away from US military contractors.
> Unfortunately, the project was cancelled for moronic political reasons.
From Wiki[1], I see: > In March 2022, in light of the Russian invasion of Ukraine, the Finnish Government declared that a rapid independence from Russian energy production is desired, and that the construction of the plant should not continue. Mika Lintilä, Finland's Minister of Economic Affairs, declared that he would not issue a construction permit.
Why is this "moronic"?[1] https://en.wikipedia.org/wiki/Hanhikivi_Nuclear_Power_Plant#...
Overall, it's not exactly a ton of jobs for how much money is going into them, but it isn't nothing.
I’m not disputing that data center buildouts will have some localized job creation, but the net effect of all those data centers will be overwhelmingly negative on employment if everything the AI companies are saying is true
Renewables can compete but take longer to build. Nuclear is more expensive and takes forever to build. Maybe SMRs will happen but I’m not holding my breath. It’s harder than it sounds to scale that.
Depending on how far north you mean, you lose all or all but one of the above.
* easy permitting
* lots of space
Something like 500g/MWh for gas/coal/nuclear (~70% of power in AZ), so a huge xAI datacenter (Colossus 2, ~1 GW/h) would use ~700 MW of this type, or ~350k gallons of water an hour, which would be 0.2% of the Colorado rivers flow rate last year.
I don't know if that's significant.
That probably matters a lot less for AI.
Pennsylvania, for example, was one of the few places to take Walmart to task for employing illegal labor.
Texas and Arizona are notoriously anti-union and anti-resident/pro-corporation.