by marksutherland · 17y ago · 0 comments
Perhaps also worth mentioning Hofstadter's Law:
"It always takes longer than you expect, even when you take Hofstadter's Law into account."
Not only does it boost the estimate enough that you're likely to hit the target, it also adds a lot of bogus precision to the numbers that the less-than-clueful will interpret as accuracy.
(Best Case Scenario + Worst Case Scenario + (4 * Most Likely))/6
I've seen reasonable estimates of 10d suddenly explode into 40+d once it makes it into upstream project plans.
Best thing to do is invest in metrics, and to revisit your estimates after the fact (nobody ever does this).