by omouse · 11y ago · 0 comments
"It will take 2 days, + 5 days, - 1 day" <-- that shows a lot of risk
"It will take 1-2 hours, + 3 hours - 0.5 hours" <-- again, showing that there's some risk
Or you push back and tell them to give you some time to form a better estimate or that you will give them an estimate update as soon as you know more.
The issue is that most software developers are not trained in how to estimate and in how to deal with these time/cost boxing scenarios. We don't attend a class like managers do on how to deal with situations like this. We have to learn as we go along.
I highly recommend Steve McConnell's Rapid Software Development, fantastic book, it has a chapter on estimation and how to deal with client's and boss's that ask for estimates.
Sometimes I get interrupted with "Alice needs X added to Y right away", or "Bob needs reassurance that this is working as intended in the original ticket" -- no problem. Other times, one might lose productivity to things like, "Java update broke our GWT compilation toolchain completely".
It helps if your manager knows that such interruptions happen, too. I also am a fan of overbudgeting and then revising later once I understand the problem better.