by strivingtobe · 2y ago · 0 comments
The "Physical Response Capacity" in that graph is the amount of capacity actually available, but it's not part of SCED. However it doesn't say anything about the timeframe it would be available in. Given that ERCOT didn't call for conservation, I would have to assume it was capacity that was "quickly available, but not cheap" rather than "not quickly available", but I don't know for sure.
Your second paragraph may be answered by this: https://www.ercot.com/gridmktinfo/dashboards/gridconditions. PRC units are available in real time, immediately on request.