by atourgates · 7mo ago · 0 comments
I just paid ~$35k (pre-now-expired-tax-break) to install a grid-tied 25kw ground mount system. I DIY'd everything except the connection between the array and the grid, which I paid an electrician to do, and the trenching which I paid my buddy with a mini-excavator to do.
It was a bit of a PITA, but mostly because I didn't finally make up my mind to do it until October and had to have it constructed by Dec 31st to take advantage of the expiring tax credit. If I'd given myself 6 months, it would have still been a big project, but way less stressful.
My neighbor's paid the same price to a contractor for a 11kw system.
Even at 46°N, and with relatively cheap electricity, my system should pay for itself in 6-8 years.
Payback time is 2-4 years.
It reminds of healthcare and infrastructure in the US. When you really dig into why both are so expensive, it's literally every step. Every link in the chain between supplier and consumer is some kind of inefficient market, or burdened by regulations, etc.
Americans are just so rich they don't care enough to see these huge margins and undercut the competition, which is what happens here and keeps markets much more efficient.
What would have been the cost if it was not DIY'd? Is this doable only in a rural/semi-urban settings?
I'm in the bay area, did a roof mount system. ~9.5kW with Enphase microinverters.
I think it cost be ~15k all in. The usual installer price is normally around $2.5-$3/w (so about $25k - $30k).
I got someone to do the plans (because I was under the gun to get on NEM2), but that was $300 well spent.
Did it all myself -- mounting, running conduit / wiring etc. Wasn't too bad. Probably about 3-4 Saturdays of work.
Here's my install log: https://www.reddit.com/r/diySolar/comments/1c6jfjv/finally_d...