The problem in ERCOT is demand massively exceeding available supply over a period of days. You need to carry your primary operating reserve all the time, because you never know when a generator or transmission line may trip.
When there's simply a lack of energy supply to meet demand on a steady state basis, you still have to preserve your primary reserves for other unexpected events and cannot call them in to meet longer term (30+ minutes) demand. So load shedding happens once available reserve dips below a certain threshold (generally around the single of the largest single contingency on the grid which may be the largest single generator or a line that feeds multiple large generators).
ERCOT hasn't run out of primary reserve, but they are going to have to shed load in order to maintain adequate reserves. You always have to shed load before exhausting reserves, because one moves you closer to stability while the other moves you further away (consuming operating reserve).
At this point, with power prices spiking to thousands of dollars per MWh, any plant that can run is running, including some that have come out of planned outage earlier to help out (and be paid handsomely). Even if you simply invoked some emergency order that "all generators must run until further notice", there simply isn't enough capacity due to the large number of generators on forced outage. There's no way out of that situation except temporary load shedding.
comment 5y ago · link · parent
I think the main issue with renewables is not inherent unreliability but that grid operators do not understand the potential contingencies as well as with conventional generation sources.
SPP has put out some good analyzes of recent max generation events there involving large amounts of wind being unavailable in cold snaps. It turns out no one at SPP bothered to ask wind turbine owners what temperatures they were capable of operating in and some wind operators didn't buy the cold weather package for turbines despite installing them in the Midwest. So generation availability forecasting didn't take into account the real capabilities of generators - a clear failure in operational planning.
This is more of a regulatory issue than a technical one. The machines can operate at -40 C, but someone has to actually spec that functionality and ensure that the associated subcomponents (heaters etc) are properly maintained.
There is a new NERC reliability standard in the drafting stage for this.
comment 5y ago · link · parent
UFLS is mostly intended to buffer transient loss of power supply (for instance, tripping of several large generators). If the grid operator knows they are facing an inadequacy of generation supply and all resources have already been called in, they will start to shed load under manual operator action to avoid UFLS activation. Before doing this they will declare an emergency which, generally speaking, requires all generators to make best efforts to supply as much energy as they can to the system.
Think of it like automated emergency braking on a car vs driver braking. AEB is great, but if you can already see that you're gonna hit something, just hit the brakes right now instead of waiting for AEB. By the time UFLS kicks in, you're already in dire straits and have only moments before reaching an unrecoverable state.
comment 5y ago · link · parent
These older phones are way more common outside of the US and even just outside of the SFBA where not everyone buys a new $1000+ phone every 2 years.
comment 5y ago · link · parent
comment 5y ago · link · parent
Since the pandemic, a lot of gas stations summarily closed their bathrooms - even to customers. It sucks.
comment 5y ago · link · parent
https://www.ctvnews.ca/politics/ottawa-gives-accounting-firm...
One of the factors cited in awarding the contract was Deloitte's "experience" doing the same thing in the USA.
http://www.canadian-accountant.com/content/business/why-delo...
comment 5y ago · link · parent
"Because we don't have the expertise to do software development."
The comments in this thread, which I fully agree with by the way, just cement my belief that if government wants to deliver high-quality IT projects they need to start developing the expertise to do it in-house.
comment 5y ago · link · parent
The main difference is that the cell network doesn't power the handset but modern cell phones use so little power than a $50 consumer UPS would recharge a cell phone many times over.
Keeping phone networks up during power outages is very important for public safety.
comment 5y ago · link · parent
What do you think of the fact that many of the products are in fact disposable by backed by a "lifetime" warranty precisely because they're so highly marked up that the manufacturer can give you a new one for free instead of attempting even trivial repairs? Osprey is the king of this. This seems to be the opposite of the buy for life mentality - things should be repaired if economical, but no one repairs what they can get replaced for free.
42.
A Nepali team has made the first winter ascent of K2(alpinist.com ↗)
304 points · by eigenvector · 5y ago · 131 comments
comment 5y ago · link · parent
comment 5y ago · link · parent
comment 5y ago · link · parent
comment 5y ago · link · parent
4 MW class onshore turbines first introduced in 2017 are just now starting to hit their stride and be installed at large scale.
comment 5y ago · link · parent
We should not conflate dams that are integral to the power system like Grand Coulee with those that are insignificant.
51.
RIP Google Play Music, 2011 – 2020(arstechnica.com ↗)
10 points · by eigenvector · 6y ago · discuss
comment 6y ago · link · parent
We have ChromeOS devices out there are perfectly able to run the latest ChromeOS in terms of specs but aren't supported anymore by Google because of an arbitrary time-based EOL and therefore will either be browsing the web unpatched or thrown away.
Whereas any other x86 computer from the last 12+ years or so can have up-to-date Windows or Linux put on it.
Another step on our march to disposable everything.
comment 6y ago · link · parent
So yes, you can legislate that. By making merchants bear the cost of defects and take a loss on replacing the product, you make it no longer a viable business model to constantly sell broken stuff. It's a proper alignment of incentives.
In a world where Google is being sued for antitrust in part because of a monopoly they built by giving stuff away for free, perhaps making it harder to have a "low margins, but we aren't accountable for anything" business is not a bad thing.
You're also building a strawman - that Google would need to spend a lot per user on customer service to start actually providing customer service instead of refusing to do so for most of its products.
It would need to spend a lot in absolute dollars, sure, but the vast majority of users would have precisely zero support interactions. No one is saying that Google should have an army of 500,000 support reps. Just that it should actually be possible to contact Google without knowing someone who works there.
comment 6y ago · link · parent
You cannot sell a defective thing then when the customer comes back say "sorry, we actually only made $0.01 on that so we don't provide customer service, goodbye."
Your obligation to not, for instance, arbitrarily revoke someone's account access causing them measurable harm is not dependent on whether you deem yourself to have a sufficient level of profit on the transaction.
Companies have obligations that external and not bounded entirely by their commercial whims.
comment 6y ago · link · parent
The design of power transmission and distribution networks is driven by several physical realities: high voltage is needed to transmit power over long distances with acceptable losses, it is easier and cheaper to transform voltage and switch ultra high power circuits in an AC network than a DC network, all power conversion is lossy, electricity is hazardous and therefore electrical circuits must be insulated and protected adequately to protect public safety.
I've heard this question of "why don't we have some kind of universal power outlet that any load regardless of voltage or current needs can connect to?" before. The answer is the same as in many other fields of engineering: it's not efficient to overbuild every node in an network to handle any possible load when electrical loads are usually well-defined and do not change rapidly. We don't have a universal train that runs in the metro, for freight and for high speed rail not because it's not possible but because that would not be efficient. The same applies here.
comment 6y ago · link · parent
Despite Intel's well-documented anti-competitive practices, AMD had decisively gained the upper hand in performance by the time of K8 (2003). Intel's microarchitecture at the time, NetBurst, was uncompetitive and relied almost entirely on inertia, and yes, anti-competitive behaviour to retain market share.
Core leap-frogged that and Intel remained ahead for the better part of a decade afterwards. To say that Intel sat on its laurels between the time of the first round of antitrust litigation in the early 90s is quite inaccurate.
comment 6y ago · link · parent
This is immensely annoying for Canadians who drive their cars to the US, although there are some built-in workarounds supported by the credit card processor such as punching in the 3 numerical digits of a Canadian postal code followed by 00.